Sec. 203.057. FEASIBILITY STUDIES  


Latest version.
  • (a) The board shall establish a process for providing to persons submitting project proposals assistance in locating a person with expertise in hydrology, water resources, or another technical area pertinent to the evaluation of water supply to conduct a feasibility study for a project using a water yield model as described by Section 203.053(b).

    (b) The board may:

    (1) dedicate a portion of the money appropriated to the board that it considers appropriate to fund part or all of a feasibility study under this section; and

    (2) establish procedures to distribute the money under Subdivision (1).

    (c) To receive funding for a feasibility study under Subsection (b), a person must submit to the board an application for funding that includes a statement of the project's anticipated impact on water resources.

Added by Acts 2011, 82nd Leg., R.S., Ch. 61 , Sec. 16, eff. September 1, 2011.