Sec. 2054.304. PROJECT PLANS    


Latest version.
  • (a) A state agency shall develop a project plan for each major information resources project or major contract.

    (b) Except as provided by Subsection (c), the state agency must file the project plan with the quality assurance team and the department before the agency:

    (1) spends more than 10 percent of allocated funds for the project or major contract; or

    (2) first issues a vendor solicitation for the project or contract.

    (c) Unless the project plan has been filed under this section:

    (1) a vendor solicitation may not be issued for the project or major contract; and

    (2) the agency may not post a vendor solicitation for the project or contract in the state business daily under Section 2155.083.

Added by Acts 2005, 79th Leg., Ch. 1068 , Sec. 1.06, eff. September 1, 2005. Amended by: Acts 2007, 80th Leg., R.S., Ch. 937 , Sec. 2.05, eff. September 1, 2007. Acts 2007, 80th Leg., R.S., Ch. 1081 , Sec. 6, eff. September 1, 2007. Acts 2009, 81st Leg., R.S., Ch. 87 , Sec. 11.021, eff. September 1, 2009.