Texas Statutes (Last Updated: January 4, 2014) |
GOVERNMENT CODE |
Title 10. GENERAL GOVERNMENT |
Subtitle F. STATE AND LOCAL CONTRACTS AND FUND MANAGEMENT |
Chapter 2267. CONTRACTING AND DELIVERY PROCEDURES FOR CONSTRUCTION PROJECTS |
Subchapter F. CONSTRUCTION MANAGER-AT-RISK METHOD |
Sec. 2267.251. CONTRACTS FOR FACILITIES: CONSTRUCTION MANAGER-AT-RISK
-
(a) In this chapter, the "construction manager-at-risk method" is a delivery method by which a governmental entity contracts with an architect or engineer for design and construction phase services and contracts separately with a construction manager-at-risk to serve as the general contractor and to provide consultation during the design and construction, rehabilitation, alteration, or repair of a facility.
(b) A construction manager-at-risk is a sole proprietorship, partnership, corporation, or other legal entity that assumes the risk for construction, rehabilitation, alteration, or repair of a facility at the contracted price as a general contractor and provides consultation to the governmental entity regarding construction during and after the design of the facility. The contracted price may be a guaranteed maximum price.
(c) A governmental entity may use the construction manager-at-risk method in selecting a general contractor for the construction, rehabilitation, alteration, or repair of a facility only as provided by this subchapter.