Sec. 2267.363. ASSUMPTION OF RISKS    


Latest version.
  • The governmental entity shall assume:

    (1) all risks and costs associated with:

    (A) scope changes and modifications, as requested by the governmental entity;

    (B) unknown or differing site conditions unless otherwise provided by the governmental entity in the request for proposals and final contract;

    (C) regulatory permitting, if the governmental entity is responsible for those risks and costs by law or contract; and

    (D) natural disasters and other force majeure events unless otherwise provided by the governmental entity in the request for proposals and final contract; and

    (2) all costs associated with property acquisition, excluding costs associated with acquiring a temporary easement or work area associated with staging or construction for the project.

Added by Acts 2011, 82nd Leg., R.S., Ch. 1129 , Sec. 2.08, eff. September 1, 2011.