Sec. 2268.058. SUBMISSION OF DETAILED PROPOSALS FOR QUALIFYING PROJECTS; EXEMPTION; COMMISSION REVIEW    


Latest version.
  • (a) Before beginning to negotiate an interim or comprehensive agreement, each responsible governmental entity receiving a detailed proposal for a qualifying project must provide copies of the proposal to:

    (1) the presiding officer of the commission; and

    (2) the chairs of the House Appropriations Committee and Senate Finance Committee or their designees.

    (b) The following qualifying projects are not subject to review by the commission:

    (1) any proposed qualifying project with a total cost of less than $5 million; and

    (2) any proposed qualifying project with a total cost of more than $5 million but less than $50 million for which money has been specifically appropriated as a public-private partnership in the General Appropriations Act.

    (c) The commission may undertake additional reviews of any qualifying project that will be completed in phases and for which an appropriation has not been made for any phase other than the current phase of the project.

    (d) Not later than the 10th day after the date the commission receives a complete copy of the detailed proposal for a qualifying project, the commission shall determine whether to accept or decline the proposal for review and notify the responsible governmental entity of the commission's decision.

    (e) If the commission accepts a proposal for review, the commission shall provide its findings and recommendations to the responsible governmental entity not later than the 45th day after the date the commission receives complete copies of the detailed proposal. If the commission does not provide its findings or recommendations to the responsible governmental entity by that date, the commission is considered to have declined review of the proposal and to not have made any findings or recommendations on the proposal.

    (f) The responsible governmental entity on request of the commission shall provide any additional information regarding a qualifying project reviewed by the commission if the information is available to or can be obtained by the responsible governmental entity.

    (g) The commission shall review accepted detailed proposals and provide findings and recommendations to the responsible governmental entity that include:

    (1) a determination on whether the terms of the proposal and proposed qualifying project create state tax-supported debt, taking into consideration the specific findings of the comptroller with respect to the recommendation;

    (2) an analysis of the potential financial impact of the qualifying project;

    (3) a review of the policy aspects of the detailed proposal and the qualifying project; and

    (4) proposed general business terms.

    (h) Review by the commission does not constitute approval of any appropriations necessary to implement a subsequent interim or comprehensive agreement.

    (i) Except as provided by Subsection (e), the responsible governmental entity may not begin negotiation of an interim or comprehensive agreement until the commission has submitted its recommendations or declined to accept the detailed proposals for review.

    (j) Not later than the 30th day before the date a comprehensive or interim agreement is executed, the responsible governmental entity shall submit to the commission and the chairs of the House Appropriations Committee and Senate Finance Committee or their designees:

    (1) a copy of the proposed interim or comprehensive agreement; and

    (2) a report describing the extent to which the commission's recommendations were addressed in the proposed interim or comprehensive agreement.

Added by Acts 2011, 82nd Leg., R.S., Ch. 1334 , Sec. 1, eff. September 1, 2011.