Sec. 755.025. INSPECTION  


Latest version.
  • (a) The executive director shall require each boiler to be inspected internally and externally at the time of initial installation and at subsequent intervals as provided by this section. The executive director may provide that the inspection be performed by any inspector.

    (b) Power boilers, unfired steam boilers, and steam collection or liberation drums of process steam generators must receive an annual certificate inspection and an annual external inspection.

    (c) Steam heating boilers and hot water heating boilers must receive a certificate inspection biennially.

    (d) Hot water supply boilers and potable water heaters must receive a certificate inspection triennially.

    (e) A portable power boiler must be inspected externally each time the boiler is moved to a new location and must receive an internal inspection at least annually.

    (f) The executive director shall designate the manner of inspection for nuclear boilers, the form of the inspection report, and the information to be reported. The executive director and the owner of a nuclear boiler shall establish the intervals of inspection for the boiler.

    (g) The executive director may authorize the inspection of a boiler at any reasonable time if the executive director determines that the boiler may be in an unsafe condition. The executive director shall notify the inspection agency that insures that boiler and request the authorized inspector employed by that agency to participate with the chief inspector or a deputy inspector in a joint inspection of the boiler not later than the 20th day after the date on which the executive director notifies the inspection agency. An additional charge may not be made for the joint inspection.

Acts 1989, 71st Leg., ch. 678, Sec. 1, eff. Sept. 1, 1989. Amended by Acts 1999, 76th Leg., ch. 352, Sec. 3, eff. Sept. 1, 1999; Acts 2003, 78th Leg., ch. 816, Sec. 26.010, eff. Sept. 1, 2003.