Sec. 254.002. PETITION FOR DRAINAGE CONSTRUCTION  


Latest version.
  • (a) The commissioners court of a county may not order a drainage system to be constructed unless a petition is presented to the court as provided by this section.

    (b) To be valid, the petition must include:

    (1) the signatures of at least 100 registered voters of the county;

    (2) a statement of the necessity for and availability of the drainage system;

    (3) the number of miles of public roads, as accurately as possible;

    (4) the width and depth of the ditches to be built along the first-class roads;

    (5) the name and location of each natural waterway crossed by the county's first-class roads;

    (6) the distance of each waterway from another along the first-class roads; and

    (7) the names and residences, if known, of each owner of real property adjacent to or within one mile of each first-class road.

Acts 1995, 74th Leg., ch. 165, Sec. 1, eff. Sept. 1, 1995.