Sec. 37.0541. CONSOLIDATION OF CERTAIN PROCEEDINGS    


Latest version.
  • The commission shall consolidate the proceeding on an application to obtain or amend a certificate of convenience and necessity for the construction of a transmission line with the proceeding on another application to obtain or amend a certificate of convenience and necessity for the construction of a transmission line if it is apparent from the applications or a motion to intervene in either proceeding that the transmission lines that are the subject of the separate proceedings share a common point of interconnection. This section does not apply to a proceeding on an application for a certificate of convenience and necessity for a transmission line to serve a competitive renewable energy zone as part of a plan developed by the commission under Section 39.904(g)(2).

Added by Acts 2009, 81st Leg., R.S., Ch. 1170 , Sec. 1, eff. June 19, 2009.